We’re going round in circles

blank
FILE: The roundabout at Grant and Walnut was opened for through-traffic on Tuesday, Dec. 19. Photo by Charles Wallace

Support Local Journalism

LOGIN
REGISTER

The roundabout on Grant Avenue at Walnut Lane opened for traffic on Tuesday morning, Dec. 19. The project was approved by the planning commission and city council in 2013. The $1,360,777 construction contract was awarded to Vintage Paving in June of this year, and construction began on Aug. 9. The lanes are 22.5 feet wide, and the speed limit is 15 mph in the roundabout. The south leg of the project is expcted to be finished this week. The center of the roundabout will be landscaped, and will be completed at a later date.